ODIM Release Management Process

Draft Dec 1, 2020

Cadence and Release Phases

Four scheduled releases each year, with two types of releases: major releases and maintenance releases (defect fixes only).

Yearly Release Cadence: 2 major releases, 2 maintenance releases

Major Release

Consists of:

Major Release Summary - Example

Aug 1 – Dec 31

Jan 1 – Jan 15

Jan 15 – Jan 30

Jan 30

Jan 31

Feature Development

MS: Feature Freeze

Integration period

integration, QA and testing

MS: RC0

Release Candidate period

Only fix blockers and
critical defects

Build the new Release

Major release goes live and is available for download


Maintenance Release

No new features. Starts after every major release and consists of:

Maintenance Release Summary Example

Feb 1 - April 15April 16-29April 29

April 30

Defect fixes

MS: RC0

Release Candidate period

Only fix blocker and critical defects

Build the Maintenance Release

General Availability of the
Maintenance Release

Announcement

Defect Severity and Definition

SeverityDefinition
Blocker
Critical
Major
Minor